Creative Carnival Kitchen Sparkles Like The North Star: Case Study

Carnival Kitchen featured in Kitchen & Bath Business magazine article

Carnival Kitchen featured in Kitchen & Bath Business magazine.

I didn’t intend for the Carnival kitchen to get national attention, but that’s what happened.

Let me explain.

I worked for a local custom cabinet maker and home remodeler as a sales-designer while finishing my design schooling. The owner expected me to schedule appointments with everyone who visited the business. One afternoon in early March, a couple came to the showroom, and we talked about their goals for remodeling an outdated kitchen. It didn’t register that they could afford a luxurious, custom kitchen with unique features because they had just started thinking about remodeling. They resisted when I asked to schedule a second meeting in their home, saying that they needed to do more looking. My boss was furious.  Although he taught me a lot about cabinetry, I didn’t particularly appreciate how my boss treated his “customers” and staff. I resigned three weeks later after he yelled at me for not meeting his sales expectations. That’s when I formed D. P. Design in April 1984.

When the couple returned to the showroom, they were told that I’d left. After seeing an article in the San Jose Mercury News about me winning the Henry Adams Award during graduation, they called me and invited me to their home to talk about what they wanted. Our meeting lasted over three hours! They had a long — and exclusive — wish list.

What features did they have to have?

Homeowners’ Wish List

  • Magnetic-induction cooktop (standard equipment today, but there was only one manufacturer at that time)
  • Gas cooktop
  • Wok (only available as commercial equipment)
  • Double ovens and a microwave oven
  • Serving cart built into the cabinets
  • Triple sink
  • Small desk
  • Walk-in pantry with dutch doors
  • Display area for their collection of Red Skelton clown figurines and plates
  • Sub-Zero built-in refrigerator
  • Sub-Zero built-in freezer
  • Countertop with two seating areas
  • A rainbow of bright accent colors — primary and pastel
  • Better lighting
  • Garden windows for daylight, display, and plants

A Dreary Kitchen Dungeon Needed Help — Lots of Help!

Springtime Carnival kitchen before remodeling

Original kitchen: a dungeon

Although it was large, the original kitchen felt like a dungeon. It had dark-stained cabinets, laminate countertops, and olive-green carpeting! Yes, carpeting! The lighting was awful. Fluorescent fixtures inside the skylight provided most of the light that glared in comparison to everything around them. Floor-to-ceiling windows in the adjacent eating area provided light during the day, but cabinets over the peninsula prevented light from getting into the kitchen. It was hard to imagine anyone working in the kitchen successfully while maintaining a good mood.

Delightful Carnival Kitchen Details

Red Skelton clown plate

Red Skelton “Freddie the Golfer” plate

The Red Skelton clown figurines and plates collected by the homeowners and fabric with a wreath of colorful flowers and butterflies inspired the “Carnival” kitchen theme. Hank Corriea and his employees used the material to create custom window treatments. Peggy Spaulding transferred the wreath motif to 12″ tiles that Fasar required with their magnetic induction cooktops.

The cabinet maker and I designed an enormous six-foot-wide custom wood hood with two exhaust fans hung above the Thermador gas cooktop and the Yick wok with a single burner rated at 36,000 BTU’s. We incorporated a unique lit display cabinet in front of the two fan ducts for the figurines and plates. Oak cabinets were still trendy, but we decided to use natural straight-grain rift oak to avoid visual overload.

Springtime carnival custom stained glass insert

Carnival Kitchen stained glass panels

Yippee! We achieved all of the homeowners’ needs and wants. My creative spirit was soaring, and we defined other “carnival” kitchen details that included:

  • Custom stained-glass inserts in the dish pantry and all wall cabinets created by Dave Benoit, backlit with automobile dome lights, made the stained glass sparkle. Remember, this was 30+ years before LED strip lighting.
  • Peggy Spaulding painted a fanciful flower-and-butterfly mural for the backsplash behind the gas cooktop and wok with the same colors as the induction cooktop tiles.
  • The contractor installed “Tivoli” rope lighting around the perimeter of the skylight.
  • Jan Moyer painted an imaginative portrait of the wife on the water heater door: she’s barefoot and pregnant, dressed as a clown, sitting on a stool with a frying pan in one hand and a golf club in the other hand. The bottom of her apron reads, “I’d rather be golfing.”

 

Carnival Kitchen Wife Clown Portrait

Wife Painted As Clown

It Pays To Work With The Best . . .

This Carnival kitchen remodeling was a magnificent opportunity to start my career! My clients and I had great brainstorming sessions, and they adopted all of my recommendations! To achieve my clients’ goals, I worked with the best people in the industry:

  • Rob, the open-minded cabinet maker
  • Peggy, the experienced tile artist
  • Dave, the detailed stained-glass master
  • Gary, the friendly appliance dealer
  • Hank, the masterful window treatment manufacturer
  • Jan, the creative trompe l’oeil painter
  • Bruce, the helpful lighting expert

. . . But There Are Always Challenges!

There were problems with this Carnival kitchen project: Because the roof over the kitchen was flat, there wasn’t enough space to install recessed light fixtures. We had to use track lighting. If we were remodeling this kitchen today, there wouldn’t be a lighting problem. About three years ago, flush-mount dimmable LED ceiling fixtures became available. There were problems with the floor installation and the tile. I proved to the homeowners that I was their advocate, and all of the issues were resolved successfully.

The Whimsical Carnival Kitchen Sparkles Like The North Star

soar like an eagle carnival kitchen

Carnival kitchen finished!

With all of the difficulties resolved, the wife said she was as happy as a child on a carousel. She admitted that they had doubts about how I would “pull off” mixing Red Skelton’s clowns into a sophisticated kitchen. An avid golfer and a lady with a great sense of humor, she was delighted with her portrait on the water heater door. She said that her husband liked all the stained-glass details, how we’d made the cabinet doors sparkle. I was delighted with their reaction and asked if I could photograph the kitchen. “Of course!” was her reply.

Two weeks later, I hired Russell Abraham, a renowned architectural photographer, to take pictures of the kitchen. His fee was three times what I charged for my design services, but it proved to be a blessing in disguise. In May 1985, two months after finishing the kitchen, I was at a national trade show. Leslie Hart, the editor of Kitchen & Bath Business magazine, approached me. We had attended the first bathroom seminar offered by Ellen Cheever, a kitchen and bath design leader who had been one of my teachers in design school.

Ms. Hart told me that I had made a good impression on her with a project I did during Ellen’s seminar and asked if I had any projects that she could publish in her magazine. I barely squeaked out the words, “yes, I do.”

“Good,” she said. “Send me a complete description of the project with all of the products you used. Don’t forget to send photos.” It took me two days to create a story about the project, entitled “Springtime Carnival.” I covered the article and the 8 x 10 photos with cardboard, then slid them lovingly into the manila envelope. Standing in line at the post office, I held the envelope over my heart and said a prayer for good things to happen.

For several weeks, I couldn’t concentrate on daily tasks because I was so excited about the possibility of being included in one of the kitchen-bath industry’s premier magazines. One month passed. Then two. Then three. I’d given up about “Springtime Carnival” ever appearing in K&BB magazine. It was early September when I got a call from Michelle Tomasik, one of the magazine’s staff writers. She wanted to verify details of the “Springtime Carnival” project for an article they might publish. She didn’t give any specific dates when the article might appear.

Be Patient. Then Follow The North Star To Success!

Again, several months passed, and I forgot about the phone call. I also forgot that the K&BB magazine’s new issues arrived in the last week of the month for the following month. In late November 1986, my husband and I decided to drive to Long Beach, California, for the first West Coast Kitchen & Bath Industry Show in early December, co-hosted by the National Kitchen & Bath Association and the K&BB magazine. They shared a sizable centrally-located booth. I wanted to see if Leslie Hart was there so that I could ask her about the article. I didn’t need to, because . . .

"Carnival" kitchen on the cover of Kitchen & Bath Business magazine

Magazine cover featuring “Springtime Carnival.”

As we approached the booth, I saw the December issue fanned out on the countertop. The “Springtime Carnival” kitchen was on the cover! And there was a four-page article inside! Whoosh! My career was off to a great start!

Remembering this one-of-a-kind Carnival kitchen still gives me goosebumps. I can’t believe that I’ve been a designer for 36 years! It’s been an incredible journey of personal and professional growth while helping others achieve their dreams. I’ve been fortunate to have many wonderful clients and fabulous projects.  There have been hurdles in my business, like the recession in 2006-2009 and the recession during the pandemic. Remembering successes like this keep me inspired and motivated to help you and others. There’s still a lot of untapped creativity inside me! Every kitchen is one-of-a-kind because your needs, lifestyle, and budget are different from everyone else in the world!

It’s an honor to share stories about real people, most who’ve overcome remodeling fears and lived through the transformation of their home and life. The articles are (and will be) about how my clients coped and what we did to achieve the best results. There will always be hints, how-tos, and tips. All of the articles will be in a particular category called “Case Studies.” I invite you to read them, leave comments, and share them with family and friends. Here’s a list of case studies:

 

Here’s the article that’s 34 years old:

"Carnival" kitchen magazine article page 1"Carnival" kitchen in magazine article, Page 2"Carnival" kitchen in Kitchen & Bath Business magazine article, Page 3"Carnival" kitchen magazine article, Page 4

Professional Tip To Achieve Remodeling Success

What I learned during this project will help you achieve what you want during the first meeting with your designer: Share everything you want to include in your project, no matter how expensive it is or how whimsical and unrealistic it seems! Of course, you can always add details during the design. But it could affect the priorities on your “wish list,” and it may require you to make tradeoffs. Remember that your designer is your facilitator, helping you to achieve your remodeling goals.

In Conclusion

The Carnival kitchen was the North Star that led me in the right direction to a successful career. I’ve had hundreds of opportunities to help homeowners achieve their dreams and goals over the past 36 years. The wonderful thing is that I still have a “creative bucket” that’s full and ready to help you with your remodeling project. Contact me for a phone call or virtual meeting to discuss your needs and intentions and what may be holding you back from achieving them. I’m here to help you — always, in all ways.

Diane Plesset, CMKBD, C.A.P.S., NCIDQ is a Homeowner Advocate who specializes in helping homeowners with remodeling and addition projects. She has been the principal of D. P. Design since April 1984. Diane is the author of the award-winning book “THE Survival Guide: Home Remodeling” and many design awards.

How Can You Avoid Construction Horror Stories?

How can you avoid construction horror stories? You can do it! These are not the typical ghost stories you hear around a campfire. But you may have heard your family and acquaintances talk about construction horror stories at social gatherings.  Exceeding the budget. Not meeting the deadline. Contractors not showing up, or doing lousy work. D-I-Y disasters. In 35 years, I’ve heard and read about and experienced similar horror stories. What makes me sad is that most of the problems encountered could have been avoided.

Avoidable Horror Story: Wallpaper That Ended Up On the Floor, Not The Wall

I worked for a custom cabinet and remodeling company after finishing design school. It was fall and business had slowed down from the peak summertime projects. A couple in Half Moon Bay, California had been saving for years and hired my employer to remodel their master bathroom. I helped them make all the product decisions which included heavily-textured vinyl wallcovering. The husband worked swing shift at the San Francisco Airport and normally got home between 1:00 and 2:00 a.m. Knowing that the project was winding down, he went into the bathroom to see what had been done when he got home from work. Later, I found out that he sat on the toilet for over four hours, watching the wallpaper slide down the walls like a slithering snake. When he called me at 6:00 a.m., it was easy to tell that he had a hard time controlling his anger.  What had happened?

I learned later that my boss had sent two of the cabinet manufacturing employees to install the wallcovering. They assumed that it was prepasted, and soaked it in water then applied it to the walls. The only thing that made the wallpaper stick to the wall was the heavy texture that acted like tiny suction cups! My boss had to replace the wallcovering, and hire a professional wallpaper hanger to redo the job that his employees had botched.  The homeowners were satisfied with the results, but not without frustration and hassles. They had done absolutely nothing wrong, assuming that my employer would take care of them in every way.

How to avoid this nightmare: Unfortunately, there’s no way for homeowners to know who a contractor has hired, unless they ask for a list of everyone who’s going to be working in their home. The important lesson is — whether it’s a contractor or a homeowner — don’t let the lure of saving money cloud an important decision that has a high probability of negative results.

A Ghoulish Tale About Lack of Communication

With my first client after establishing D. P. Design, I learned the importance of communication among the remodeling team members. The homeowners had a general contractor who they wanted to hire. They demanded to hire an independent electrician for their project instead of letting the general use one of his subs.  I didn’t realize until later what a problem it would create. The G.C. and the electrician refused to communicate. Everything seemed to be progressing smoothly until a heavy storm system rolled through our area. The day before, the electrician was penetrating the roof and running wires into the kitchen and didn’t tell anyone about the holes he’d created. The contractor called me to report that the new custom cabinets were all wet. He demanded that I call the electrician and the homeowners to report what had happened, to let them know that he wasn’t going to clean up the mess.

The homeowners were caught in the middle of a dog fight.  They demanded that the electrician pay the G.C. for cleaning up the job site and repairing the roof. Fortunately, the cabinets weren’t damaged.

How to avoid horror stories like this: Ask questions — lots of them! Discover if the contractor you’re hiring has employees and regular subcontractors. More important, talk with the contractor about tradespeople or suppliers you know. Be especially careful about hiring friends or family members to work on your project. These relationships have a high failure rate.

The Root of Most Construction Horror Stories: D-I-Y

In the past 35-plus years, I’ve heard and read about D-I-Y horror stories, and I’ve lived them firsthand. Often, the decision to tackle a project is driven by the need or desire to save money. But homeowners can also be lulled into a false sense of  “I/we can do this!” — especially after watching how easy a project seems to be on TV or videos on the internet.  My husband and I have had our share of construction horror stories. Most of these nightmares happened because we thought we could save money. We didn’t!

I’ve written about D-I-Y remodeling disasters before! Read this blog for more information! I’ve also written about the problems created by remodeling reality shows setting homeowners up for serious problems.

Floors are a BIG Challenge For D-I-Yers!

We had major problems refinishing the wood floors in our first home.  Looking back on it, we can laugh. But at the time, it was not funny. The first disaster was when we were refinishing the floors in a den adjacent to the entry hall that we intended to convert to a dining room. The oak strip floor had been covered with carpeting and needed to be freshened up. My husband did the sanding around the perimeter of the room. I decided to sand the middle of the room with the drum sander we’d rented, while he was at work.  Everything was going fine until I had to change the sandpaper and didn’t pay attention to how the metal plate held the sandpaper in place. When I turned on the machine again and started moving the sander across the floor, I noticed big chunks of the floor were being spewed out. The screws that held the plate in place were digging and carving the floor with every pass! There was nothing to do but pay a flooring company to extend the parquet from the entry hall into the dining room.  It turned out beautiful, but it was an expensive learning lesson.

Did we learn a lesson? Yes, and no. We didn’t make the same mistake when we refinished the floors in my home office, but that project turned into a horror story, too. After we sanded the floor, we decided to work together to apply the urethane. I was on my hands and knees with a wide brush intended for refinishing floors. My husband stood over my shoulder and carefully poured puddles of urethane that I then spread uniformly. So what was the problem? I noticed that no matter how hard I tried, there were millions of “fuzzies” in the finish. My husband was wearing wooly socks! We had to re-sand the floor and vacuum it thoroughly before applying the urethane. This time, my husband was barefoot! We got the results we wanted, but it cost more for extra days for the drum sander rental, plus more urethane. And it nearly tripled the amount of time we’d allotted to do this project.

A friend of ours had a floor refinishing disaster when he was doing repair and maintenance for his landlord in exchange for a lower rent. He lived in a beautiful Victorian three-story home that had been converted into apartments. Victorian homes are known for rich and ornate woodworking that includes heavily-carved wainscoting and moldings. Everything seemed to be going fine — didn’t we just read this? — until the drum sander stopped working. Dead. Then Ed remembered the age of the building and realized that he’d probably blown a fuse. So he went down to the electrical panel in the basement and verified that he had blown a fuse. Fortunately, there were spare fuses available, so he replaced the bad fuse with a good one. Immediately after the last turn of the fuse, he heard the drum sander come to life over his head. Although he immediately ran up the stairs, he was too late to stop the mess that the sander had created. It had bounced off the walls, tearing up all the beautiful woodwork, and dug a trench in the floor.

“Let’s Take Out This Wall” D-I-Y Near-Disaster

Homeowners called me to help them solve a problem they’d created. Empty-nesters with a five-bedroom home, they decided to convert a bedroom that was adjacent to their master bedroom into a sitting room. They bought or borrowed a sledgehammer, and on a Saturday morning, the husband started swinging the massive tool of destruction at the wall between the two rooms. After removing several studs, he heard the ceiling and roof creaking and groaning, and he could see the ceiling sagging. He realized that he was taking out a bearing wall! He immediately grabbed a hammer and nails and reinstalled the studs to stabilize the structure. When I met with the couple, we talked about what needed to be done: hire a structural engineer and a contractor so they could have the master suite they desired. It was relatively easy, and the end results were wonderful. They didn’t know what they didn’t know, and they hadn’t thought about everything before they started removing the bearing wall. They ended up replacing the carpeting in both rooms because they didn’t realize that there would be a gap where the wall had been.

Hints, How-To, and Tips for D-I-Yers

How To Avoid D-I-Y Disasters: Yes, it’s difficult. But not impossible! Before tackling any D-I-Y project, we need to research the logical steps involved and the tools required. We also need to read about other people’s experience with a similar project. The biggest challenge to overcome is our mindset.  What’s really driving the need to do the work instead of hiring a professional? There are many reasons why homeowners get trapped by D-I-Y projects, but the most obvious one is money, or the lack of funds to hire a professional. Before doing the work, think about how much you have for the project, and how much you think you’re going to save. Statistics verify that most D-I-Y projects end up being a higher investment than the budget allotted. Often, the actual investment exceeds what homeowners would pay a professional to do the work. Additionally, it usually takes three to four times as long for homeowners to achieve the results they think they want.

One of my first instructors in design school frequently said, “There are only two ways to pay for anything. You can take it out of your bank account, or take it out of your hide.”  Not all D-I-Y projects are disasters. Successful projects are most often done by people who know their strengths and weaknesses. My husband is an excellent tile setter. Slow, yes. But he takes his time to do it right and gets consistently straight grout joints. And he’s a master with a spray gun, whether it’s applying paint to a room or lacquer to cabinets. But I don’t let him lay his hands on rollers and brushes!  He’s also very knowledgeable about anything electrical or electronic. Because of his talents, we’ve saved a bundle of money over the years.

I’m going to be brutally honest. As a D-I-Yer, you’re not likely to achieve the same results that a professional would, in the amount of time it would take a professional to do the job. What is your time worth? Are you willing to live with a daily reminder of a botched job? My husband says this often, mostly in reply to a “honey-do” request: “If you want a professional job, hire a professional.” Here’s one of my favorite quotes that apply to virtually all construction horror stories:

The bitterness of poor quality lingers long after the sweetness of low price is forgotten.”

In Conclusion

What I shared with you is a very small sampling of construction nightmares that I’ve heard and read about. To satisfy curiosity before writing this blog, I did an internet search for “construction horror stories” which yielded millions of results. But reviewing the past 35 years in this business, the number of successes that my colleagues and I have achieved exceeds horror stories by a ten-to-one ratio.  To be perfectly honest, I believe that there are very few absolute successes and absolute failures.  The desire, the hope for success is what keeps us all moving forward.

Listen To The Podcast: Construction Horror Stories

I can and will help you with your home building or remodeling project! I truly care about helping you stay within a reasonable budget and achieve the best results possible. Contact me today! Let’s talk about your goals.

Kitchen Remodeling Expectations: Honest, Reliable Input

Kitchen Remodeling Expectations: Honest, Reliable Input

Kitchen remodeling expectations is a subject I talk about with homeowners at every first meeting with them. It’s not uncommon to hear this comment, “We’ve called several contractors about our kitchen, but they’re all busy right now.” The logical follow-up question is, “When do you want to start your project, and when do you want it finished?”

“When Do You Want Your Kitchen Remodeling Project Finished?”

Often, I hear this reply, “We want to start immediately, because we want our kitchen finished by the Holidays,” which usually means Thanksgiving. If you’ve just started on the journey to a remodeled kitchen and want your kitchen completed by Thanksgiving 2019, I’m sorry to tell you that it’s too late to be contacting contractors. Why?

How Long Does a Standard Kitchen Remodeling Project Take?

From start to finish, a standard kitchen remodeling project takes about 8 weeks to complete, if there are no structural changes, special features, or unforeseen challenges to overcome. To finish your kitchen the week before Thanksgiving, the contractor has to begin construction no later than October 3. If you’ve hired your design professional and contractor, and start planning today, August 6, you have less than a month to make hundreds of decisions about your kitchen remodeling for your designer to complete the plans before September 3 to allow time for plan check.

Here is a list of what happens before construction:

  1. Decide what you want, how much you want to invest, and when you want your remodeling project completed.
  2. Interview kitchen design professionals to find the best match for your needs.
  3. Make decisions about the scope of work and products that will be included in your kitchen remodeling.
  4. Interview contractors to find the best match for your needs.
  5. Prepare plans for estimates, permits, and construction.
  6. Get permits.

The Value of a Professional Kitchen Designer

Why should you hire a professional kitchen designer first? When you call contractors, they’ll ask if you have plans. Contractors know that you’ll expect an estimate. They also know that plans will help them prepare the estimate with more accuracy. Without plans, all they can give you is a “guesstimate,” a wide range of investment based on their experience, or the “Cost vs. Value” report. A kitchen designer has the training and experience to help you with all of your decisions and prepare the necessary plans, and much more, according to the National Kitchen & Bath Association (NKBA). I’ll write and talk more about this in the very near future.

Realistic Time Allowances

Assuming that you’ve already hired a kitchen design professional who’s working on your plans, how long do you think it takes to hire a contractor? The quickest turnaround time I’ve ever experienced is three weeks from the first meeting until my clients hired the contractor who I recommended. We gave him a set of the preliminary plans, then he gave copies of the plans to his electrician, plumber, cabinet maker, and countertop fabricator for reliable numbers. Then he compiled the information into a detailed written estimate. If you’re interviewing multiple contractors, this step could stretch to several months.

It can take as little as one month to finalize the plans for permits and construction, but it can take longer than six months. Why? This relates to the amount of time you need to make decisions about all of the products for your kitchen remodeling project. The final plans should reflect every decision you’ve made. This assures that you’ll get the results you expect from your remodeling team. Here’s a list of your major decisions that should be included in the plans that are submitted for permits and construction:

  • Scope of your project (what you want to achieve, your goals)
  • Windows, doors, and skylights
  • Appliances
  • Cabinets
  • Plumbing fixtures
  • Countertops and backsplash
  • Flooring and other surface finishes
  • Lighting
  • Special details

Decisions! Decisions! Decisions!

Bottom line, you need to make decisions about all of the products, and the products should be ordered as soon as possible. Everything should be at the jobsite the day your contractor arrives with sledgehammer in hand to start demolition.

Everyone makes decisions in their own way. Only you know how easy or difficult it is for you to make decisions. This isn’t going to change. It’s part of your nature, and it’s okay. Do you like to take time to think about and investigate all options before making a decision? Or do you know that you want “Option A” the minute you see it? The amount of time required to make decisions directly impacts how long it takes to finalize your plans.

Allow Time For Plan Check

After your plans are completed, the Building Department has to check the plans so they can issue permits. It takes them about one month to review plans for “standard” projects. If your contractor is going to start construction on October 3, your plans must be submitted to the Building Department before September 3. If you can bear to read/hear this, I highly recommend that you take time to plan ahead for your home remodeling, and really be ready to “rock and roll” after the first of the year, or even into the springtime when the weather will be more cooperative.

Current Kitchen Remodeling Project

I just went through this process with current clients who decided to wait until spring to remodel their kitchen. It’s a good thing they did, because we ran into a challenge that caused delays in their appliance decision. In our first meeting, they expressed the desire for white appliances, including an induction range and a 33” wide french door refrigerator without ice and water in the door. After two weeks of searching and shopping, trying to find a white induction range, they decided to switch to stainless steel appliances. They finalized their decision about the range, hood, dishwasher, and the microwave oven, but the refrigerator became our next hurdle. The wife took on the monumental task of making a detailed spreadsheet of all the refrigerators available in their preferred style and size. Her spreadsheet included:

  • Dimensions
  • Storage area (cubic feet)
  • Fingerprint shield, yes or no
  • Consumer Report rating
  • Number of buyer reviews and overall rating

This is the type of research that I gladly do for my clients, to help them make informed decisions. It’s wonderful when clients take on a proactive task like this, but many homeowners don’t have the time or inclination, and prefer to pay me to do the research.

Kitchen Remodeling Schedule Setbacks

The timelines I’ve used assumes that construction will proceed smoothly. It might, but it might not. There are many unforeseen challenges that can affect a project at any time. Working within such a tight schedule, under pressure, important details can fall through the cracks, especially as we approach the holidays.

My award-winning book, “THE Survival Guide: Home Remodeling,” contains a multitude of stories about clients’ remodeling projects. I’m reminded of one kitchen in particular, that was scheduled to be finished before Thanksgiving: Homeowners made decisions about all of the products for their new kitchen. They hired a contractor and ordered all of the products. I finished the plans and the Building Department took only two weeks to issue permits. The contractor started work the week after Labor Day. Everything was going smoothly, until one of the subcontractors came to work although he wasn’t feeling well. He had the flu. Everyone involved with the project, including yours truly and the homeowners, got the bug. Of course, this set the project back about three weeks. The homeowners and their son celebrated Thanksgiving with the husband’s family.

Summary: Kitchen Remodeling Requires Realistic Expectations

In conclusion, it’s very important to plan ahead for your kitchen remodeling project, to follow logical steps I’ve outlined from the day you decide that you want to remodel. Allow yourself valuable time to make all your decisions. If you do this, you’re increasing your chances for successful results without hassles and regrets.

8/6/19 Podcast: Kitchen Remodeling Expectations: Honest, Reliable Input

I’m available to personally walk you through all of the steps of your kitchen remodeling project! Call me today! Let’s chat about what you want, when you want it, and how much you want to invest.

Remodeling Questions and Answers

Kitchen After Remodeling

Two important remodeling questions happen  during first meetings with homeowners. They’re great questions! Sometimes I have to do research to answer a remodeling question specifically, but I love to do research because it provides information and builds confidence. For the two important remodeling questions,  I have answers that I’ve already researched and proved to be accurate.

REMODELING QUESTION #1:

“How long will it take to complete our project?”

There are two parts to the answer. The answer to the first part of the “how long will it take?” remodeling question focuses on how long it will take to complete the design phase of a project. There is no pat answer for this question, because it depends totally on the following four reasons:

Reason #1: How long it takes for homeowners to make decisions.

I’ve had clients who made decisions at lightning speed, and other clients who needed to think about every aspect of a decision. It’s totally personal. If you’re the type of person who needs all available information before you make a decision, then the design process will take longer, which will ultimately affect the start and finish dates for construction.

Reason #2: Meeting schedules.

In the perfect world, homeowners and their design professional should have regular meetings to stay on track. I like to meet with my clients weekly, but sometimes it’s not possible. I remember one couple who had very busy career schedules that involved a lot of travel. We were lucky to have one meeting a month! Unfortunately, a good percentage of the time was spent recapping what we’d discussed at the last meeting before we could proceed talking about other aspects of their project.

Reason #3: Building the “team.”

I like to get a contractor involved in the process as early as possible, so he or she can offer valuable information about the project. Scheduling meetings with contractors can consume a significant amount of time, but it’s necessary to help homeowners select who they’re going to hire.

Reason #4: Financing.

If you need or want to finance your project, start talking with financial institutions as soon as possible. Getting approved for a home equity loan can take a month or more, as current clients are discovering.

Specific Answers to Remodeling Question #1:

How long construction will take depends upon the size of your project. Allow at least:

  • 6 weeks for a guest bathroom or a powder room.
  • 8 weeks (minimum) for a master bathroom.
  • 8 – 10 weeks for a kitchen without an addition.
  • 12- 16 weeks for a kitchen with an addition.
  • 6 – 10 months for a major whole-house remodel with an addition.

Variables That Affect How Long Construction Will Take

Weather conditions

Unseasonable storms can play havoc with a project schedule. Weather in other parts of the country (or world) can affect transport of a particular product.

Product availability

Order all products well in advance of the construction start date and store them at the jobsite or get a definite delivery date for appliances, cabinets, and large plumbing fixtures. This is advice that many homeowners take lightly. Several times in my career, clients delayed their project because they neglected to select and order products. For some reason,  light fixtures cause a lot of anxiety.

When a supplier tells you that a product is “in stock,” it’s important to find out where it’s stocked and how long it will take to get the product to your home.

Unforeseen emergencies

All of the contractor’s employees and subcontractors got the flu. This delayed clients’ project for almost two months. The HVAC contractor caused delay of new home construction when his employee forgot to renew his boiler license.

Unforeseen framing problems

During demolition, discovering things like dry rot, termites, and poor framing can seriously affect the schedule, depending on the severity of the problem.

“While you’re here . . .”

When homeowners change their minds or add to the project scope, it can seriously affect the finish date. Contractors can also delay the project when they make recommendations that they know will increase the homeowners’ investment. Several years ago, my client’s contractor said to him,  “We can easily add a rooftop deck so you can enjoy the sunsets.” Fortunately, I learned about the conversation and asked the contractor to provide a written change order for the additional materials and labor plus an estimate of how much time it would add to the project completion. After seeing the change order, my client decided not to go ahead with the roof deck.

REMODELING QUESTION #2:
“How much will our project cost?”

The second important remodeling question that homeowners ask at the first meeting is, “How much will my project cost?” I recommend a shift in thinking from “cost” to “investment.” You are, after all, making an investment to  improve your home, and improve your lifestyle. That’s a worthwhile investment!

While I’m on the subject of changing your mindset, I’d like to recommend that you think of financial numbers you get from a contractor as an estimate, not a bid. There is a lot of competition among contractors who want you to hire them, but it should never become a bidding war.

Specific Answer to Remodeling Question #2 — A Great Tool

We’re fortunate to have a wonderful tool available to all of us, called the Cost vs. Value Report that’s been produced yearly since around 2001.  Why is it such a valuable tool? It provides:

  • A complete list of different home improvement projects, large and small.
  • Valuable investment and return-on-investment information for every region, and major cities within that region. You can see how your investment compares in your city to other cities in the region, and how your investment compares to national averages.
  • A description of the materials that are included and the square footage of the project. You can then derive a reasonable square footage investment for your project and do some basic math to help you define your budget.

When you click on the link to access the Cost vs. Value Report, after you select the city, the website will divert you to a page that requests demographic information. In all the years I’ve been using this report and referring it to hundreds of homeowners, no one has ever complained about ending up in  a “sales cycle” by sponsors of the report. If you do get unwanted sales contacts from any of the advertisers, please let me know and I’ll intercede on your behalf.

Remodeling Questions and Answers: A True Story

What follows is a true story about one project that was as good as it can get from beginning to end.

I met with homeowners in early April two years ago. They’d been thinking about and talking about remodeling their 1970s kitchen for several years and were prepared to get started immediately. After telling me how they wanted their new kitchen to function and look, they asked the two important remodeling questions that I’m accustomed to hearing.

When the wife asked remodeling question #1, “How long is it going to take to remodel our kitchen?” I had to preface my answer with a warning. Most contractors I knew were already scheduling projects to start in the fall and later, so they may not achieve their new kitchen until the following year. Their facial expressions clearly showed their disappointment, but the husband’s follow-up comment was optimistic, “I’m sure the right contractor is out there.” This motivated me to work hard and find the right contractor for them. Because their project also included updating the rest of  their home, I told them that their project would probably take three to four months instead of the normal eight to ten weeks. We agreed that it would be great to find an available contractor who was also a good project manager.

Then the husband asked remodeling question #2, “How much will we pay for all of this?,”  I shared what I knew from the “Cost vs. Value” report, that their kitchen remodeling project would be around $70,000, but the investment in the additional updating would bring the total to $130,000 or more. They were surprised that the number was so high, but took this information graciously. Honestly, at the end of the meeting, I wasn’t sure whether they would proceed with their project or not, but I really wanted to help them.

For the next several days, I contacted every contractor who had worked with me on projects in the past ten years, except the ones who I vowed to never work with again. You may know the type; they don’t:

  • Provide accurate investment estimates.
  • Know how to schedule a project and keep it on track.
  • Have good communication skills.
  • Have employees or subs that work on all their projects.
  • Follow the details in design plans.
  • Respect homeowners’ property.

Yes, it’s true that I’ve worked with the best and the worst. The best will take the most challenging project and turn it into a dream-come-true. The worst will take any project they touch into a nightmare.

Found: A Great Contractor!

One of the contractors I contacted, Larry Mock, the principal of Cascade Custom Remodeling, had a large project fall through at the last minute because his clients got transferred to Southern California. He was available! Not only that, but I rediscovered what a professional he is. I was so excited, I called the homeowners. The wife answered and immediately said, “I was just about to call you and schedule our next appointment so you can take measurements of our home!” Talk about pieces of a puzzle falling together!

Larry met with the homeowners three weeks later, after I finished the preliminary plan, elevations, and perspectives. He prepared a detailed eight-page breakdown of their investment, and gave them a preliminary schedule.

The Project: On Time, Within A Reasonable Budget

In the three weeks that followed, I worked with the homeowners to select all of the products for their home. It was a real joy working with them! They were always upbeat and optimistic about everything! And they made quick decisions! At the same time, I finalized the design plans that included several virtual-reality perspectives. Here’s one of the perspectives I prepared:

Virtual-Reality Perspective

Larry finalized his estimate. Construction proceeded smoothly. Larry stayed on top of the schedule and communicated with everyone daily. It looked as if the project would be completed on schedule, in late September, until one of the fabricator’s employees dropped the table top. This meant that  the fabricator had to re-make the table top using a new slab. The fabricator squeezed new the table into their schedule and installed the replacement slab in less than a week.

The design phase for this remodeling project took only six weeks from the day I took measurements until I gave the final plans to the homeowners and Larry. Construction started on July 7 and final inspection happened on October 5, three months from beginning to completion. The homeowners’ total investment was $135,350.00.

Remember The Results

It’s gratifying when a project finishes on time within a reasonable budget, and gives homeowners the results they want. I’m happiest when I provide honest, reliable information that helps homeowners make informed decisions. This was one of the projects that I’ll always remember as an achievable goal when all of the stars align. It started with two important remodeling questions about “When?” and “How much?”

–oOo–

See the before and after photos of this project in my Portfolio.

Like my blogs? Like my podcasts? Tell everyone you know about them! Follow me on Social Media: Facebook, Houzz, LinkedIn, Twitter, and YouTube.

“Today’s Home” Podcast: Remodeling Questions and Answers

Also remember that I’m available to help you with your project, from beginning to end! Contact me today to talk about your remodeling (or building) project.

Kitchen Remodeling Codes

Function and Safety Are #1!

While working with a young couple, a serious issue arose about code compliance.

During our first meeting, I was told that the entire extended family enjoys working in the kitchen together. As a designer, I immediately consider what this means when safety, functionality, and overall concept is included. So, in my reply, I cited the aisleway clearances recommended by the National Kitchen & Bath Association (NKBA):

  • The minimum for a one-person access between countertops is 42”;
  • Access increases to a minimum of 48” if multiple people are working in the kitchen simultaneously.

These guidelines allow safe usage of appliances, and unlimited access to everything stored in cabinets.

The homeowners requested a four-foot wide by eight-foot long island. Their kitchen is narrow – only 13′-11” wide, with no room for an addition. Fortunately, the length of the kitchen is generous.

Important Calculation For Island Function & Safety

Back in my office, the first thing I did was to calculate the kitchen island size that would be safe and functional as well as beautiful. Here is my math:

167” (width of the total available space in inches)

– 51” (cabinets and countertops on both sides)

116” (space available in the center of the room)

-84” (two 42” wide aisleways)

32”   (2′-8” available space for the island)

I sent an email with these unfortunate results of my calculations. They were not happy, and repeated the desire for a four-foot wide island. I shared information about the appliances which would be on both sides of the kitchen. Each appliance needs space for accessibility, which I took into consideration as I worked out the numbers above. This is actually one of the many aspects where my years of education and design experience comes in handy. In an NKBA seminar, I learned from Ellen Cheever to show all appliance doors open in my plans. Homeowners can see how much clearance they have between objects. Oven and dishwasher doors can take 24” or more from an aisleway. Refrigerator doors vary from as little as 18” to over 36”, depending on the manufacturer and model.

Although my clients wanted the larger island, we were able to proceed through the logical design steps. With careful planning, I was able to give the homeowners 42” aisleways on both sides of the island. I reduced one partial wall of cabinetry to 12” deep for a wine bar and pantry. The double ovens were placed adjacent to the end of the island.  Someone can now access the oven door head-on, which is normal and safe. It is especially important to provide this head-on access so that a homeowner can cook and access something heavy, like a Thanksgiving turkey, or something awkward, like a casserole or a large sheet of cookies. I allowed an aisleway of 4′-10” along the cooktop wall, from the oven to the main sink on the opposite wall. This area could become seriously congested with multiple users.

NKBA Guidelines for Kitchen Aisleways

I use the guidelines developed by the NKBA as a standard practice in every kitchen (or bathroom) design. I learned them over 25 years ago when preparing for my certification tests. And I still use them because they verify industry standards for safety and function. I have discussed this in articles I’ve written in the past. In “The Kitchen Triangle: A Guideline,” I state that Function and Safety have to be designed into a project from the get-go. Appearance should be determined after everything is deemed to be functional and safe. I later wrote another article, “Kitchen Islands May Not Be Appropriate For Every Home,” in which I share the guidelines for walkways and island design.

Recently, this client requested that I move the island closer to the cooktop, which would eliminate frontal access to the oven. This would require her and other family members to access the oven from the side, tweaking their backs while using the oven. Now, no matter how young and healthy or agile one feels, others using the kitchen (parents, aunts, uncles, etc.) may not have the strength to use the oven without injury if there is no head-on access. Additionally, changing access to the oven can affect the resalability of the home. The kitchen is a huge selling point in any home. So, I was unable to acquiesce to this request. I shared the NKBA Guideline #6 which has graphics to show the intent of the guideline. Here’s the text of this guideline and the code:

Citation: Guidelines and Code

Work Aisle – Recommended: The width of a work aisle should be at least 42” for one cook and at least 48” for multiple cooks. Measure between the counter frontage, tall cabinets, and/or appliances.

Access Standard – Recommended: Kitchen Guideline recommendation meets Access Standard recommendation. See Code References for specific applications.

Code Reference: A clear floor space of at least 30” x 48” should be provided at each kitchen appliance. Clear floor spaces can overlap. (ANSI A 117.1 305.3, 804.6.1)

As a Certified Master Kitchen-Bath Designer, I consider myself an extension of the Building Department, to protect the health, safety, and welfare of homeowners. It’s my duty and responsibility to be familiar with and to comply with all codes. I cannot, and will not, turn my back on these duties and responsibilities for any client. But first, I try to help them understand that I’m not a stubborn bureaucrat, that I have their best interests in my mind and heart. Theodore Roosevelt said it best:

“Nobody cares how much you know, until they know how much you care.”

Yes, I care — a lot! That’s why I am sharing this story to help you understand that professional designers have to balance creativity and code knowledge, while trying to give their clients what the clients want, often within a limited budget. It sure isn’t an easy career path, but I still love it!

Homeowner Tips:

  • You’ve hired a professional designer to help you. Listen to them, and take their recommendations seriously, because they have your best interest as a goal.
  • If the design professional gives a recommendation without a valid reason, ask for the reason. A valid reason IS NOT: “This is the way we always do it.” A valid reason IS: “This is the code,” or “This is based on the NKBA Guidelines for function and safety.”
  • Remember that Function and Safety are the #1 priority in all remodeling, especially bathrooms and kitchens. Appearance can be any color or style after function and safety are verified.

If you’re thinking about remodeling your kitchen (or bathroom), please call me! I care about your health, safety, and welfare, and I want to help you achieve your remodeling goals!

Remodeling A 1970s Home For Special Needs

A family of six lived in a 1970s home that needed major remodeling, Here are the challenges and solutions that would transform the home totally:

Challenges and Solutions

#1: The youngest son has muscular dystrophy and cannot get to the large basement playroom without being carried by the father.

A residential elevator would allow the son to travel easily to and from the main floor to the basement. The best location for the elevator shaft was at the rear of the home, with entries to the elevator in the living room and the play room.

#2: The front had an uninviting stone wall that hid the entry door.

Removing the wall and changing the front of the house would make the home more inviting for guests.

#3: The existing kitchen was too small, especially for entertaining.

The kitchen would be moved to the existing family room, so the existing kitchen could become the dining room, allowing the homeowners to entertain more frequently.

#4: The existing master suite was typical for a 1970s home, with a small shower and a one-person lavatory. Closets were small, with limited storage. The only linen storage was a small closet in the main hallway.

An addition solved all of the problems. The master bedroom is bigger, and there are two large closets with lots of storage. The new bathroom has a two-person shower, a separate toilet room, and large separate lavatories. There’s also a 6-foot wide linen closet.

BONUS: The addition also created a great bedroom for the oldest daughter in the basement area that gave her the privacy she needed; it has a wonderful view of the garden.

#5: The youngest son’s bedroom and the guest bathroom needed to be remodeled to be accessible. The bathroom also needed to look nice for guests.

Transforming a 30” door into a 36” door required borrowing space from the existing small linen closet. The bathroom remodel became part of the master suite addition, making room for a 5-foot wheelchair turnaround, and easy access to the tub/shower and the toilet.

*DESIGN TIP: A “handicap” bathroom doesn’t need to look or feel like a hospital! There are many beautiful products available that blend with a home’s style and the family’s preferences.

The Design And Value Engineering

I worked with the family for about three months to develop the preliminary plans and prepare virtual-reality renderings to show them what their remodeled home could look like. They loved it! Before we got involved with choosing products, I recommended a contractor who could provide a detailed estimate. We call this “value engineering.” This would help the couple know what their investment would be. Estimates this early in the process helps homeowners make important decisions about the scope of their project before they get too excited about their project.

The preliminary estimate, with allowances for products and finishes, approached $500,000. Talking with the couple honestly, we all agreed that if they remodeled this home, it would most likely be their final home.  The reason: they wouldn’t be able to get any return of their investment when comparing their home to neighboring properties. They admitted that it was important to go through the initial process like we did, although it involved an investment of about $3,000. But it helped them make the important decision to look for a home that had all of the amenities they needed and wanted. Fortunately, they found a new home in a neighboring community that had everything, including a residential elevator! Their investment in the new home was more than their total investment of the existing remodeled home would have been.  But considering the disruption of their lives during a major remodel, they decided it was worth selling their home and moving to the new home.

A Special Bonus For The Homeowners

What we didn’t realize was that the proposed plans and virtual-reality renderings that I had put into a binder for them would help to sell their home in three days for the full asking price! This was confirmation that it’s hard for most people to visualize the possibilities and see past the existing reality. I’m so grateful to have a career, where my ability to see the possibilities helps people to move forward.

Design Tips From This Project

It’s best to get a contractor involved early in the process, to provide value engineering for the project, and verify that what you want is within your budget. Most contractors charge a fee for this service, but many apply all or part of the fee towards construction of your project. There will be tradeoffs involved, but tit’s important for you to:

* Establish a realistic, reasonable budget.
* Make informed decisions about the scope of your project and all products.